All publications by tag «ITER»
2024, January, 18, 06:45:00
RUSSIAN DEVELOPMENT FOR ITER
For the ITER project, which is under construction in Cadarache in southern France, Russia's responsibilities include manufacturing 179 of the most energy intensive (up to 5 MW per square metre) panels of the first wall, which is 40% of the total area of the reactor wall.
2022, October, 11, 17:10:00
RUSSIAN EQUIPMENT FOR ITER
In total, Russian enterprises have manufactured and shipped more than 1,000 pedestals. The ITER Design Centre, a private institution under Rosatom, performs the functions of the Russian National Agency for ITER, responsible for ensuring Russia's in-kind contribution to the project.
2022, August, 9, 14:10:00
RUSSIA FOR ITER FUSION
The 25th batch of Russian electrical equipment was successfully delivered to the construction site of the international thermonuclear experimental reactor Iter in France,
2022, July, 14, 12:00:00
ITER FUSION DELAYING
ITER is a major international project to build a tokamak fusion device in Cadarache, France, designed to prove the feasibility of fusion as a large-scale and carbon-free source of energy.
2021, March, 19, 12:40:00
CHINA'S TRITIUM FOR ITER
A tritium breeding blanket is a core component for future fusion reactors to realise tritium breeding self-sufficiency and electricity generation
2021, February, 24, 10:40:00
ITER FUSION FUNDING EUR 5.61 BLN
The ITER agreement was signed in November 2006 by Euratom, the US, Russia, Japan, China, South Korea and India.
2020, July, 29, 11:35:00
ITER FUSION ASSEMBLY
Launched in 2006 and based in southern France, the International Thermonuclear Experimental Reactor (ITER) had planned to test its first super-heated plasma by 2020 and achieve full fusion by 2023.
2020, June, 1, 09:55:00
ITER FUSION MACHINE
The milestone marks the installation of the first and heaviest component of the ITER fusion machine.
2019, October, 9, 13:00:00
ITER, CNPE CONTRACT
A contract for Tokamak machine assembly for the ITER International Fusion Energy Organisation signed by a consortium led by China Nuclear Power Engineering Corporation (CNPE) is the biggest nuclear energy project contract that Chinese companies have ever bid for in the European market.
2019, October, 2, 11:10:00
ITER FUSION ENERGY
The ITER International Fusion Energy Organisation has awarded a EUR200 million (USD218 million) contract for the Tokamak Assembly (TAC2) to Dynamic. The operation will mostly be performed at the ITER site in Cadarache, France with the engineering and manufacturing support of Dynamic's founding companies - Ansaldo Nucleare, Endel Engie, Orys Group ORTEC, SIMIC, Leading and Ansaldo Energia.