PLATTS - Russia's Novatek is set to start exporting LNG from its third 5.5 million mt/year train at the Yamal LNG project by the end of 2018, CEO Leonid Mikhelson said late Monday.

The LNG producer has brought all of its Yamal LNG trains on track ahead of schedule, with guidance previously stating that the third train would begin commercial operations at the start of 2019.

Speaking on the sidelines of the Gastech conference in Barcelona, Mikhelson said Novatek could review its strategy to reach 57 million mt/year of LNG production by 2030 in the coming years as it continues to expand its already huge gas resource base in northern Russia.

He also said he expected some 80% of its future LNG production to serve the Asian market, with future sales to China in the local Yuan currency under consideration.

"In 2021, or 2022, we may review our strategy to reach 57 million mt/year by 2030," Mikhelson said.

Novatek brought online its first 5.5 million mt/year LNG train at the three-train Yamal LNG facility in December last year, and has since commissioned the second train.

The company is also close to making final investment decision on a new LNG plant -- Arctic LNG 2 -- which would have a production capacity of 19.8 million mt/year.

"We expect to take FID in the middle of next year, and definitely before the end of the year," Mikhelson said.

FIDs on new LNG supply projects have become increasingly scarce following the fall in LNG prices on the back of an oversupplied market, and expectations of a supply glut persisting well into the 2020s.

Novatek, however, is moving forward with its plans on the expectation of growing LNG demand. Mikhelson said global LNG demand could even reach 700 million mt/year by 2030 as new countries begin LNG imports.

ARCTIC LNG 2 PARTNERS

Novatek has yet to finalize the partnership structure for Arctic LNG 2, but with FID planned for mid-2019, Mikhelson said the ownership of the plant would be set following the completion of FEED work.

"We have decided to keep 60% for ourselves -- that is the current plan -- having already sold 10% to Total," he said.

"We are negotiating with a number of other companies," he said, including Saudi Aramco and China's CNPC, which have expressed interest in the project.

"All potential partners have studied the upstream part of the project, and in the next three weeks we will complete the FEED work, and they will want to see the results before making a final agreement," he said.

Mikhelson said he was confident that Novatek would be able to bring costs down for each train as the company develops new plants, with Arctic LNG 2 set to be 30% cheaper, in terms of capital expenditure, than the $28 billion Yamal LNG plant.

External financing for Arctic LNG 2 would be required for no more than 30% of the total budget, he said.

TRANSSHIPMENT POINTS

As well as producing LNG, Novatek is planning two transshipment centers -- one in the east in Kamchatka and one in the west at Murmansk -- to optimize shipping.

Novatek can use its chartered icebreaker fleet to export LNG to the transshipment centers from where it can load it onto conventional LNG tankers.

Mikhelson said work to build the Murmansk transshipment point had already begun with commissioning set for the end of the first half of 2019.

-----

Earlier:

 RUSSIAN LNG UP
2018, September, 3, 15:00:00

RUSSIAN LNG UP

REUTERS - Liquefied natural gas exports from Novatek’s Yamal terminal in the Arctic have come on stream faster than expected over the summer and exceeded volumes from Russia’s only other LNG facility, Sakhalin, for the first time in August.

 

 ЯМАЛ СПГ - 2 ВКЛЮЧЕН
2018, August, 10, 09:50:00

YAMAL LNG - 2 LAUNCHED

NOVATEK - PAO NOVATEK announced that Yamal LNG has launched the second LNG train and dispatched the first cargo from this unit. The second LNG train commissioned six months ahead of its original schedule, and combined with the first LNG train launch in December 2017, has achieved the commissioning of the first two LNG trains in record time.

ПРИБЫЛЬ НОВАТЭК 32 МЛРД. РУБ.
2018, July, 27, 12:10:00

NOVATEK'S PROFIT RUB 32 BLN

NOVATEK - In the second quarter and the first half of 2018, profit attributable to shareholders of PAO NOVATEK increased to RR 32.0 billion (RR 10.63 per share), or by approximately ten-fold, and to RR 75.2 billion (RR 24.93 per share), or by 1.2%, respectively, as compared to the corresponding periods in 2017.

 РУССКИЙ СПГ ДЛЯ КИТАЯ
2018, July, 23, 13:30:00

RUSSIA'S LNG FOR CHINA

NOVATEK - PAO NOVATEK (“NOVATEK” and/or the “Company”) has shipped its first cargos of liquefied natural gas (LNG) from the Yamal LNG project to China via the Northern Sea Route.

 ДОБЫЧА НОВАТЭК: +2,4%
2018, July, 12, 10:10:00

NOVATEK'S PRODUCTION: +2.4%

NOVATEK - In the first half 2018, NOVATEK’s hydrocarbons production totaled 264.3 million barrels of oil equivalent (boe), including 32.93 billion cubic meters (bcm) of natural gas and 5,864 thousand tons of liquids (gas condensate and crude oil), resulting in an increase in total hydrocarbons production by 6.3 million boe, or by 2.4%, as compared to the first half 2017.

 ВЗАИМОПОНИМАНИЕ НОВАТЭК И KOGAS
2018, June, 25, 12:05:00

NOVATEK - KOGAS UNDERSTANDING

NOVATEK - According to the MOU, the parties agreed to explore opportunities for KOGAS to enter the Arctic LNG 2 project and possible LNG off-take from the project, participate in the LNG transshipment project in Kamchatka and other infrastructure projects, as well as develop cooperation in LNG trading and logistics optimization, including swap operations.

 СОГЛАШЕНИЕ НОВАТЭК - TOTAL: $25.5 МЛРД.
2018, May, 25, 10:30:00

NOVATEK - TOTAL AGREEMENT: $25.5 BLN

NOVATEK - At the 22nd Saint Petersburg International Economic Forum, in the presence of the President of Russia Vladimir Putin and the President of France Emmanuel Macron, Chairman of the Management Board of PAO NOVATEK (“NOVATEK”) Leonid Mikhelson and Chairman and Chief Executive Officer of TOTAL S.A. (“TOTAL”) Patrick Pouyanné signed a binding agreement on the terms to enter the Arctic LNG 2 project.

 

 