BRITAIN OFFSHORE WIND 1.5 GW

BRITAIN OFFSHORE WIND 1.5 GW

ENERDATA - 12 February 2026 - The UK has granted development consent to the 1.5 GW Outer Dowsing offshore wind park off the east coast of England (UK Government press release, 10/02/2026). The project is being developed by TotalEnergies, Corio Generation, their affiliates, and Thailand's Gulf Development.

This consent allows the project to build and operate up to 100 turbines with associated infrastructure. Underground onshore cables will transmit power from the landfall site near Anderby Marsh (north of Skegness) to a new substation at Surfleet Marsh in South Lincolnshire.

A final decision was initially due by 10 October 2025, after the Planning Inspectorate completed its six-month examination of the DCO application in April 2025. The deadline was later extended to 10 February 2026 to allow time for additional information requests and consultations.

The project did not secure a Contracts for Difference contract in Allocation Round 7 (AR7) and will be eligible for AR8. The UK awarded 8.4 GW of offshore wind capacity in AR7 in January 2026 (KEI, 15/01/2026) and targets 43-50 GW of offshore wind capacity by 2030.
-----


Earlier:

BRITAIN OFFSHORE WIND 1.5 GW
2026, February, 10, 12:45:00
BRITAIN'S ENERGY INVESTMENT $1.4 BLN
Britain is seeking to largely decarbonise its power sector by 2030, which will require a big increase in renewable capacity.
BRITAIN OFFSHORE WIND 1.5 GW
2025, October, 20, 07:40:00
BRITAIN: EXTREME CLIMATE
Britain should brace for warming of at least 2 degrees Celsius by 2050 and as much as 4C by the end of the century, the Climate Change Committee said in a letter on Wednesday. It was responding to a request for advice from the government about likely future climate scenarios.
BRITAIN OFFSHORE WIND 1.5 GW
2025, August, 15, 06:15:00
BRITAIN'S FUSION PROJECTILE
Instead of using complex and expensive lasers or magnets to generate or maintain the conditions for fusion, FLF compresses the fuel inside a target using a projectile travelling at tremendous speed.
BRITAIN OFFSHORE WIND 1.5 GW
2025, March, 13, 06:40:00
BRITISH SPACE FUSION
The Sunbird concept is for the fusion-powered 'tugs' to be permanently based in space, able to dock on to spacecraft and propel them at high speed over vast distances. Pulsar Fusion says it foresees a compact nuclear fusion engine providing both thrust and electrical power for spacecraft, including as much as 2 MW of power on arrival at a destination.
BRITAIN OFFSHORE WIND 1.5 GW
2025, February, 27, 06:40:00
BRITAIN ELECTRICITY PRICES UP
Ofgem's new cap of 1,849 pounds ($2,334.18) a year for average use of electricity and gas is up 111 pounds, or 6.4%, from 1,738 pounds under the previous cap.
BRITAIN OFFSHORE WIND 1.5 GW
2025, January, 24, 06:40:00
BRITAIN FUSION INVESTMENT £410 MLN
The UK government has announced a £410m investment to advance the development of nuclear fusion energy and boost economic growth as part of its Plan for Change initiative.
BRITAIN OFFSHORE WIND 1.5 GW
2024, December, 6, 06:25:00
BRITAIN NUCLEAR EXTENSION
Just last week, the Britain Remade campaign group said hitting the UK's target for a clean energy grid by 2030 will be "almost impossible" without extending the operation of some of the country's nuclear power plants.
BRITAIN OFFSHORE WIND 1.5 GW
2024, November, 21, 06:25:00
BRITAIN NEED LNG
This would put the UK's import levels at their highest since February, when it took 991,000 mt of LNG. The country has seen particularly low LNG demand since Q2 of 2024; however, that seems to be shifting as it procures more winter cargoes.
All Publications »
Tags: BRITAIN, WIND, RENEWABLE